How long does a heat pump installation take?

A typical domestic heat pump installation takes 2–3 days. More complex installations, such as those requiring significant pipework changes or multiple radiator upgrades, may take a little longer.

What happens during installation:

  • Day 1 — the outdoor unit is positioned and mounted on its base. Pipework is run from the outdoor unit to inside the property. The hot water cylinder is installed.
  • Day 2 — the heat pump is connected to your heating system. Any radiator upgrades are carried out. Electrical connections are completed.
  • Day 3 — the system is filled, tested, and commissioned. We set up the controls, walk you through the system, and make sure everything is working properly.

What affects the timeline:

  • Radiator upgrades — if several radiators need replacing, this adds time
  • Pipework complexity — the distance between the outdoor unit and your heating system
  • Electrical supply — if your consumer unit needs upgrading to accommodate the heat pump

All work is carried out by our own qualified engineers. We keep disruption to a minimum and always leave your home clean and tidy.

Got more questions?

Call us on 01786 357014 or get a free proposal — no obligation.

Proud Partners with the Industry's Leading Brands

We are officially trained and approved to install equipment from the most trusted names in renewable energy. This is your assurance of a quality installation and a fully-protected warranty.

Tesla Powerwall logo
Give Energy logo
Tesla Energy
Andersen EV logo
SolarEdge logo
Myenergi logo
Pod Point logo
Hypervolt logo
Easee logo
Wallbox logo
Solis logo
Tesla Powerwall logo
Give Energy logo
Tesla Energy
Andersen EV logo
SolarEdge logo
Myenergi logo
Pod Point logo
Hypervolt logo
Easee logo
Wallbox logo
Solis logo